Editor's Choice


Execution of the massive Azmet Reactor project DRC

First Quarter 2024 Editor's Choice News & events

The Azmet Reactor project, a collaborative effort led by Viva Engineering, involved fabricating six massive reactors that were over three stories high in Gauteng, and then transporting these more than 2500 kilometres to a mine in the DRC - where all 3265 parts fitted perfectly, with not even one of the 26 900 bolts out of place. This was a massive achievement. This is according to Amanuel Gebremeskel, CEO of the Southern African Institute for Steel Construction (SAISC).

“The project entailed detailed design, complex geometry with finite element modelling, and an integrated support frame and platform. It exemplified precision engineering, showcasing intricate design and fabrication processes. To appreciate the complexity, consider that they had to plan, design and fabricate huge modular structures ahead of time, in such a way that they could be moved through four or five different countries by road to install on site at the mine,” Gebremeskel says.

He explains that the more conventional approach would be to use heavy concrete tanks, or set up a substantial design office and fabrication works with a highly skilled team, both of which are not readily available locally in the DRC. Using an established South African fabricator, based in Gauteng, therefore provided a viable alternative. This allowed for a controlled environment and close monitoring to ensure that all construction materials and structures met the required quality and safety standards.

Poring over the project

The Azmet Reactor project not only involved creating six huge reactors, but also several other complex tanks, platework, and plant buildings. From a technical point of view, engineers had to consider the design of the vessel in relation to permanence, material, equipment, and wind loads. Due to the nature of the spliced connections, these had to be modelled in detail, including all the bolts. Furthermore, as the vessels had to be transported and erected piece by large piece, a lifting study first had to be performed. This focused on the selection of the most appropriate lifting methodology, considering that the reactor components would need to be loaded onto conventional heavy-duty transport vehicles. On the opposite end, at the mine in the DRC, careful consideration was given to the constructability of the project.

Shaping up and shipping out

Gebremeskel says that the aspect of this project that stood out the most during the judging process was the logistics. “They designed each large structure in a modular fashion, for ease of transport and installation. However, bear in mind that these structures had a diameter of 9,9 metres and a height of 11,6 metres, which is almost the size of a three-storey building.”

The road transportation therefore necessitated exacting tolerances to ensure safe and timely delivery to site in the DRC. Transport jigs were designed and built to brace the components and reduce vibration during transportation, while meticulous load packing optimised weight distribution for the lengthy trip. The components of each reactor were packed so that upon arrival on site they could be assembled from the designated package. The components also had to be carefully packed in specially designed cradles to optimise each load and minimise the number of loads to site.

“The essential brilliance of this project lay in the smooth coordination and orchestration of design, fabrication and erection. The process was perfectly choreographed by the project managers, who oversaw the planning down to the finest detail,” Gebremeskel observes.

Reactors are essentially large tanks that are custom-made to remove precious metals from mined ore, and must tolerate a variety of different temperatures and chemicals. A rubber bladder required to protect the steel from these compounds therefore also had to be installed prior to leaving the Viva Engineering workshop in Gauteng.

Gebremeskel says that adjectives such as ‘innovative’ and ‘ingenious’ come to mind. “The lining was put on the inside to protect the steel from whatever solvent was being used. As one can imagine, it was necessary to do some fairly detailed mockups, and even trial assemblies to test this. The reactors were eventually bolted together. This meant that the lining had to work in a bolted tank rather than a conventionally welded one,” he explains.

Maintaining the continuity of the rubber lining between the bolted faces of each component was successfully addressed, as the project brief explains: “The first reactor was trial assembled to prove that the jigs and manufacturing were correct. All six rubber-lined reactors were installed without a single flange hole out of place. Rubber lining is continuous on the bolted faces. This required that the fabrication details incorporated the lining thickness. During fabrication, spacer plates were also inserted in the connections to simulate the lining. Corrosion protection was furthermore applied to the external surfaces of the component”.

Joining quality with manufacturing excellence

Yet another innovative aspect of the Azmet Reactor project was the precision welding required to join the panels during the fabrication process, so they could be bolted together once on site. The level of welding precision and accuracy had to be very high, as the structures could not distort during the transportation process.

“The design had to cover exactly how to lift and manoeuvre these large and very heavy modular structures. The most significant load was during the lifting process − as opposed to when they were in use − entailing a very different kind of engineering. The entire design was driven by the plans to construct and then transport each structure, as opposed to its ultimate application,” Gebremeskel continues.

The benefits of steel in this project were numerous, as detailed in the project brief: “The complexity of the reactor geometry is best suited to fabrication in steel. Construction of the reactors in concrete would not be viable due to the complexity of formwork and deployment of plant onto a site of limited size. The benefit of steel for this application is a relatively lightweight structure (compared to concrete), which can be preassembled and trial-erected before being transported to site. This allows for fast and accurate erection in the final location.”

A precise and praiseworthy precedent

One of the chief challenges was completing the project on time, as late delivery would have resulted in substantial penalties. Needless to say, timeous delivery was achieved against all odds.

“The Azmet Reactors project represents a veritable feat of engineering – showcasing brilliance of design, logistics and installation – and demonstrating the South African steel sector’s capability to execute structurally and logistically complex projects with precision. This is a victory for our industry, and could certainly not have been achieved elsewhere on the continent. Considering the number of mines being constructed throughout Africa, the good news is that similar projects will no doubt be required, which our local steel supply chain can certainly deliver,” he concludes.

For more information contact Kendal Hunt, +27 11 462 6188, [email protected], www.kendalhunt.co.za




Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Pushing technological boundaries with Festo Electric Automation solutions
Festo South Africa Editor's Choice
In the ever-evolving landscape of Industrial Automation, Festo Electric Automation solutions are at the forefront of a revolution, fundamentally reshaping production paradigms. As a global leader in automation, Festo focuses on intelligent connectivity to reduce costs, save time, and increase efficiency and convenience for customers.

Read more...
Perfect balance for every race
Horne Technologies Editor's Choice Electrical switching & drive systems & components
It goes without saying that success in Formula 1 requires a top driver. However, their chance of achieving a place on the podium depends on the car, which in turn depends on three essential factors: engine, tyres and aerodynamics. To find the optimum balance, the racing teams test models of their bolides in the wind tunnel. At Sauber, the adjustable components are moved on the model and in the test chamber using FAULHABER motors.

Read more...
MeerKAT radio telescope array
Editor's Choice News & events
Leading consulting engineering and infrastructure advisory practice, Zutari is continuing its involvement with the world-leading MeerKAT radio telescope array, where it has played a leading role since the project first broke ground.

Read more...
Top 10 emerging technologies
Editor's Choice
The World Economic Forum (WEF) has identified ten technologies likely to make a significant positive impact in the next three to five years. These are detailed in the ‘Top 10 Emerging Technologies’ report, which explains each technology’s potential for addressing global challenges and the factors that will shape the future and revolutionise connectivity still further.

Read more...
Electrifying the future
Parker Hannifin - Sales Company South Africa Editor's Choice Electrical switching & drive systems & components
A revolution is underway, transforming the way we power compact construction machines and heavy-duty mobile machinery. This is the electrification of equipment, a movement propelled by the need for environmental sustainability, lower emissions, reduced noise levels, and the pursuit of a cleaner, greener future.

Read more...
How to clean compressed air effectively
Editor's Choice
SO-Reliability Partners has taken another step in bringing to market highly effective solutions to combat contamination in all its forms. The locally designed and patented Air Wizard inline water trap is proudly manufactured in South Africa. It has been SABS tested for the separation of water, oily fluids, rust and solid particulates from pneumatic compressed air or gas lines.

Read more...
New Black Bruin hydraulic motors for heavy-duty applications
Axiom Hydraulics Editor's Choice Hydraulic systems & components
Axiom Hydraulics and Black Bruin have been working together since the late 1990s, serving southern Africa’s fluid power, mining, industrial, agriculture and marine industries. Now Black Bruin is extending its rotating shaft motor portfolio. With a patent pending design, the new X-series is engineered to enhance the performance of both new and existing machinery in terms of durability, serviceability and cost-effectiveness.

Read more...
Quality gearboxes for agriculture
SEW-EURODRIVE Editor's Choice Electrical switching & drive systems & components
Offering a complete gear solution for centre pivot irrigation systems, SEW-EURODRIVE brings its quality products and support as an original equipment manufacturer (OEM) closer to South Africa’s farming sector.

Read more...
Robotic solution for adhesive tape application with flexible control
Beckhoff Automation Editor's Choice Robotics & Mechatronics
In industry, even elaborate processes, such as the application of adhesive tape to parts with varying geometries are automated. Innovative Automation has developed a platform with Beckhoff control technology and a remote feeding module, which increases productivity and enables flexible customisation for different requirements.

Read more...
The information explosion
Editor's Choice Other technologies
The world has a data storage problem. There’s an explosion in the volume of data being generated and stored, and it’s rising exponentially. Fortunately, organisations are beginning to test new storage technologies like DNA storage, glass storage, neuromorphic computing, and extreme parallelism in order to keep up.

Read more...